Meadow Ridge ResortEgg Harbor, Wisconsin – Door County

PROJECT SCOPE

On 3/21/01, Wieser Concrete was contacted by Bill Baudhuin about a new poured-in-place tank that had collapsed due to the soil load. The tank held 65,000 gallons and needed to be replaced. We proposed using precast tanks – for a total of 66,000 gallons.

  • 3 – 18,000 Holding Tanks
  • 1 – 12,000 Holding Tank
  • These tanks were used because:
    • they were competitively priced,
    • had adequate capacity,
    • could be installed within the timeline (wanted tank replaced within 1 month)
    • state pre-approved
    • pre-engineered to withstand loading condition

PRODUCT PRODUCTION REQUIREMENTS

  • All tanks hooked together with connecting pipes on bottom so they would fill and empty through one inlet (fill) and one pump-out port (empty).
  • Product was ordered 4/4/01 and delivered 4/17/01.

INSTALLATION TIMELINE

  • Tanks were delivered, set in place and pipes hooked up in 5 1/2 hours.

OTHER

  • Engineer:Baudhuin, Inc. Sturgeon Bay, Wisconsin
  • Contractor:Parent Construction, Inc. Baileys Harbor, Wisconsin