Fort Snelling National Cemetery ExpansionMinneapolis, Minnesota

PROJECT SCOPE

  • 10,500 Pre-Placed Burial Vaults

PRODUCT PRODUCTION REQUIREMENTS

  • Product was produced and delivered in 15 weeks.

INSTALLATION TIMELINE

  • Installation began 4 weeks after production began and was completed in 11 weeks.

OTHER

  • In-house form engineering and manufacturing enables production expansion as project requires.
  • Dependable product quality has meant fewer construction problems for contractor allowing project to be completed on time.
»