Rural Development Wastewater Cluster System Elk River, Minnesota

PROJECT SCOPE

  • 3 – 20,000 Gallon Tanks

PRODUCT PRODUCTION REQUIREMENTS

  • Tanks and accessories were produced to engineering specifications.
  • Tanks were ordered October 18, 2002 and delivered to jobsite on November 11, 2002.

INSTALLATION TIMELINE

  • Tanks were delivered and installed in one day.

OTHER

  • Engineer: John Oliver & Associates, Elk River, MN
  • Contractor: West Branch Construction Rice, MN