PROJECT SCOPE:

ON 3/21/01, WIESER CONCRETE WAS CONTACTED BY BILL BAUDHUIN ABOUT A NEW POURED-IN-PLACE TANK THAT HAD COLLAPSED DUE TO THE SOIL LOAD. THE TANK HELD 65,000 GALLONS AND NEEDED TO BE REPLACED. WE PROPOSED USING PRECAST TANKS – FOR A TOTAL OF 66,000 GALLONS

  • 3 – 18,000 HOLDING TANKS
  • 1 – 12,000 HOLDING TANK
  • THESE TANKS WERE USED BECAUSE:
  • THEY WERE COMPETITIVELY PRICED,
  • HAD ADEQUATE CAPACITY,
  • COULD BE INSTALLED WITHIN THE TIMELINE (WANTED TANK REPLACED WITHIN 1 MONTH)
  • STATE PRE-APPROVED
  • PRE-ENGINEERED TO WITHSTAND LOADING CONDITION

PRODUCT PRODUCTION REQUIREMENTS:

  • ALL TANKS HOOKED TOGETHER WITH CONNECTING PIPES ON BOTTOM SO THEY WOULD FILL AND EMPTY THROUGH ONE INLET (FILL) AND ONE PUMP-OUT PORT (EMPTY)
  • PRODUCT WAS ORDERED 4/4/01 AND DELIVERED 4/17/01

INSTALLATION TIMELINE:

  • TANKS WERE DELIVERED, SET IN PLACE AND PIPES HOOKED UP IN 5 1/2 HOURS

OTHER:

  • ENGINEER:BAUDHUIN, INC. STURGEON BAY, WISCONSIN
  • CONTRACTOR:PARENT CONSTRUCTION, INC. BAILEYS HARBOR, WISCONSIN