Wastewater Treatment Facility Project

Underground Profiles

Wastewater Treatment Facility Project

WASTEWATER TREATMENT FACILITY LAPORTE, MINNESOTA

PROJECT SCOPE:

  • 2 – 18,000 GALLON RECIRCULATION TANKS
  • 2 – 6010 GALLON SEPTIC TANKS
  • 1 – 1,000 GALLON SETTLING TANK
  • 1 – 6000 GALLON GREASE INTECEPTOR
  • 48 – 1,000 GALLON SEPTIC TANKS

PRODUCT PRODUCTION REQUIREMENTS:

  • TANKS AND ACCESSORIES WERE PRODUCED TO ENGINEERING SPECIFICATIONS.

INSTALLATION TIMELINE:

  • TANKS WERE DELIVERED AND SET AS NEEDED BY CONTRACTOR.

OTHER:

  • ENGINEER: THATCHER ENGINEERING, MINNEAPOLIS, MN
  • CONTRACTOR: UTILITY SYSTEMS OF AMERICA, EVELETH, MN