Multiple Large Tank Project

Underground Profiles

Multiple Large Tank Project

ANOKA HENNEPIN ELEMENTARY SCHOOL RURAL DEVELOPMENT WASTEWATER ANDOVER, MINNESOTA

PROJECT SCOPE:

  • 1 – 15,000 GALLON DUAL COMPARTMENT SEPTIC TANK
  • 1 – 12,000 GALLON SAND FILTER DOSING PUMP STATION
  • 1 – 12,000 GALLON DOSING STATION

PRODUCT PRODUCTION REQUIREMENTS:

  • TANKS AND ACCESSORIES WERE PRODUCED TO ENGINEERING SPECIFICATIONS.
  • 4 DAY PRODUCT PRODUCTION

INSTALLATION TIMELINE:

  • TANKS WERE DELIVERED AND SET IN 1 DAY

OTHER:

  • NORTH AMERICAN WETLAND ENGINEERING
  • J.R. FERCHE, INC., RICE, MINNESOTA