Pre-placed Burial Vault Project

Share

Pre-placed Burial Vault Project

FORT SNELLING NATIONAL CEMETERY
CEMETERY EXPANSION
MINNEAPOLIS, MINNESOTA

PROJECT SCOPE:
  • 10,500 PRE-PLACED BURIAL VAULTS
PRODUCT PRODUCTION REQUIREMENTS:
  • PRODUCT WAS PRODUCED AND DELIVERED IN 15 WEEKS
INSTALLATION TIMELINE:
  • INSTALLATION BEGAN 4 WEEKS AFTER PRODUCTION BEGAN AND WAS COMPLETED IN 11 WEEKS.
OTHER:
  • IN-HOUSE FORM ENGINEERING AND MANUFACTURING ENABLES PRODUCTION EXPANSION AS PROJECT REQUIRES.
  • DEPENDABLE PRODUCT QUALITY HAS MEANT FEWER CONSTRUCTION PROBLEMS FOR CONTRACTOR ALLOWING PROJECT TO BE COMPLETED ON TIME.